February 2020


7th Slab WIP / 6th Slab Completed

7th Slab WIP / 6th Slab Completed

Brick Work 1st Floor WIP

Club House Plaster Completed

January 2020


Childrens Play Area

Building no 2, 7th Slab WIP

Building no 2, 7th Slab WIP

Building no 2, 7th Slab WIP

Club RCC Completed Plaster Progress

December 2019


5th Slab Completed / 6th Slab WIP

5th Slab Completed / 6th Slab WIP

Skating Ready

Open GYM Ready

Childrens Play Ready

November 2019


Building no: 2 - 4th slab completed /5th WIP.

Building no: 2 - 4th slab completed / 5th WIP.

Cricket Turf Ready

Cricket Turf Ready

Cricket Turf Ready

October 2019


Pathway to site.

Bldg No 2 - 3rd slab completed

Jogging Track WIP

Clubhouse 1st Slab completed

Garden WIP

Garden Night view

August 2019


Termix Road work completed.

Bldg No 2 - 1st Slab Completed.

1st Slab Club House WIP.

June 2019


Bldg No 2 Phase II plinth.

Bldg No 7 Entrance Lobby.

DG Backup for the site.

Bldg No 3 Grill work completed.

Garden WIP.

May 2019


Bldg No 3 ready.

Bldg No 4 ready.

Bldg No 7 ready.

Tremix work of concrete road ready.

Bldg No 2 plinth.

April 2019


Bldg No 4 Painting Work Completed.

Part of tremix work of concrete road in periphery of the society ready.

Part of tremix work of concrete road in perphery of the society WIP.

Bldg No 3& 4 Backside painting work completed.

March 2019


WIP of tremix work of concrete road in perphery of the society.

WIP of tremix work of concrete road in perphery of the society.

WIP of tremix work of concrete road in perphery of the society.

WIP of tremix work of concrete road in perphery of the society.

WIP of tremix work of concrete road in perphery of the society.

February 2019


Bldg No 4 Texture Paint Completed.

January 2019


Bldg No 2, Plinth Work Completed

Bldg No 3, Painting Work Completed

Bldg No 4, Texture Paint WIP

December 2018


Bldg No 7 Sliding Work completed

Bldg No 3 External Painting WIP

Bldg No 2 Plinth WIP

Compound Wall WIP

October 2018


Bldg No 3 Painting WIP

Bldg No 7 Painting work completed

Club House Plinth work completed

September2018


Bldg No 7 Painting WIP

Club House Plinth

Bldg No 7 Painting WIP

Compound Wall

Garden Excavation

Garden Compound Wall

August 2018


Club House Plinth Work in Progress.

Garden Wall created

July 2018


Bldg 4 Brick work completed

Club House work in Progress

May 2018


Bldg No 4 Brick Work in Progress

Bldg No 7 - Flooring Work in Progress

Bldg No 3 - Plaster Completed

April 2018


Main Gate

Main Gate

Bldg No 7 Texture Completed

Bldg No 3 Plaster in Progress

Bldg No 4 Plaster in Progress

March 2018


Building No 7 Texture Work on Process

Building No 3 & 4 Slabs Completed

February 2018


Bldg No 7 Texture Applying

Bldg No 4 All Slabs Completed brick work on progress

Bldg No 3 Plaster on Process

January 2018


Entrance Gate

Entrance Garden

Bldg No 3

Sample Flat Ready

Bldg No 7

Escavation of Club House

Bldg No 3 & 4

Bldg No 7

December 2017


Bldg No 3

Entrance Gate

Bldg No 7

November 2017


Building 3 brickwork completed till 6th floor

Building 4 7th slab completed

October 2017


Building 3 9th slab (terrace) work in progress

Building 3 brickwork completed till 5th floor

Building 4 6th slab completed

September 2017


Building 7 external white wash painting completed

Building 3 terrace slab (8th slab) completed

Building 4 6th slab WIP

August 2017


Building 4 5th slab ready

Building 7 external plaster completed

July 2017


Building 4 4th slab ready

Building 7 external plaster WIP

Building 3 7th slab WIP

June 2017


Building 7 terrace elevation WIP & brickwork completed till 7th floor

Building 3 5th slab ready

Building 4 3rd slab ready

May 2017


Building 7 external brickwork completed upto 5th floor

Building 4 3rd slab work in progress

April 2017


Building 3 4th slab ready

Building 4 2nd slab ready

Building 7 8th slab ready
 
 

March 2017


Building 7 7th slab ready

Building 3 3rd slab ready
 
 

February 2017


Building 7 6th Slab casting done

Building 3 2nd Slab casting done

Building 4 1st Slab casting done
 
 

January 2017


Building 7 4th slab WIP

Building 3 1st slab casting
 
 
 

December 2016


Building 7 front view

Building 7 3rd slab casting
 
 
 

November 2016


Building 7 front view
 
 
 

October 2016


Building 7 2nd slab WIP

Building 3 plinth WIP

Building 7 Plinth PCC work in progress

June 2016


Buildings 3 & 4 footing work started

Building 7 Backfilling in progress